2.3.3.2 ProtoNode RER: S0 – S3 and A1-A8 DIP Switch Locations
The S-Bank DIP switches are accessible through the top cover. However, the cover must be
removed to access the A1 through A8 switches. To remove the cover, pull it from the unit while
holding onto the 6 pin Phoenix connector.
IMPORTANT!
Do not hold the wall mount tabs when removing the cover as these
are designed to break off if not required!
Location of DIP Switches S0 – S3 and A1-A8
2.3.3.3 ProtoNode LER: S0 – S3 DIP Switch Configuration Settings
S0 S1 S2 S3 Profile
1 ACS/BMS II/BMS, 4 C-More Controlled Boilers
1 ACS/BMS II/BMS, 8 C-More Controlled Boilers
1 ACS/BMS II/BMS, 12 C-More Controlled Boilers
1 ACS/BMS II, 4 Modulex Boilers With BCMs
12 C-More, 6 ECS/SP, 4 Modulex and 2 ACS/BMS II
Switches
Switches
(S0, S1, S2, S3)